Before a new part goes into regular production, the customer needs evidence that the supplier understands every requirement and can meet them consistently. The PPAP process, short for Production Part Approval Process, is the standard way to provide that evidence. It brings together drawings, risk analyses, measurements, and sample parts into one submission that the customer reviews and approves.
This guide explains what PPAP is, the 18 elements it can include, the five submission levels, and when a new submission is required.
What is PPAP?
PPAP is a structured method, published by the Automotive Industry Action Group (AIAG), for showing that a production process can make parts that meet the customer’s engineering and quality requirements at the planned rate. Although it began in the automotive supply chain, many manufacturers in industrial equipment, electronics, appliances, and other sectors now use it, either as written or adapted to their own needs.
The key point is that PPAP evaluates the process, not just a handful of good parts. The parts submitted must come from production tooling, production materials, and the actual process that will be used for regular orders.
How PPAP relates to APQP
Advanced Product Quality Planning (APQP) is the broader framework for developing a new product and its manufacturing process. It runs through five phases: planning, product design and development, process design and development, product and process validation, and feedback and corrective action. PPAP is the formal output of the validation phase. In other words, APQP is how the team prepares, and PPAP is how it proves the preparation worked.
The 18 elements of a PPAP submission
Not every submission includes all 18 elements. The customer decides which ones apply, usually through the submission level. The full list is:
- Design records, including drawings and specifications
- Authorized engineering change documents
- Customer engineering approval, when required
- Design FMEA, if the supplier is responsible for design
- Process flow diagram
- Process FMEA
- Control plan
- Measurement system analysis (MSA) studies
- Dimensional results
- Records of material and performance test results
- Initial process studies
- Qualified laboratory documentation
- Appearance approval report, when appearance matters
- Sample production parts
- Master sample
- Checking aids
- Customer-specific requirements
- Part Submission Warrant (PSW)
The Part Submission Warrant is the summary document that ties everything together. The supplier signs it to declare that the parts meet all requirements, and the customer’s approval of the PSW is what releases the part for production.
The five PPAP submission levels
| Level | What the supplier submits |
|---|---|
| Level 1 | Part Submission Warrant only, plus an appearance approval report if applicable |
| Level 2 | PSW with product samples and limited supporting data |
| Level 3 | PSW with product samples and complete supporting data |
| Level 4 | PSW and other requirements as defined by the customer |
| Level 5 | PSW with product samples and complete supporting data, reviewed at the supplier’s manufacturing location |
Level 3 is the default when the customer does not specify otherwise. At every level, the supplier is expected to keep the full set of records on file, even if it does not send all of them.
How the PPAP process works step by step
The process usually starts when the customer issues a purchase order or a design release and states the submission level. The supplier then builds the process documentation: the process flow, the PFMEA that identifies what could go wrong at each step, and the control plan that describes how each risk is controlled.
Next comes a production run using the real process. The AIAG manual describes this as a significant production run, typically between one and eight hours of production with at least 300 consecutive parts, unless the customer agrees to something different. Parts from that run are measured against every characteristic on the drawing, tested as required, and used for the process capability studies.
Capability is often expressed as Ppk. In the AIAG guidance, a Ppk above 1.67 generally meets acceptance criteria, a value between 1.33 and 1.67 may be accepted with the customer’s agreement, and a value below 1.33 calls for corrective action. Customers can set their own limits, so the purchase order or quality agreement always takes priority.
Finally, the supplier compiles the package, signs the PSW, and submits it. The customer reviews it and approves, approves on an interim basis with conditions, or rejects it with feedback.
When a new PPAP is required
A submission is not a one-time event. Suppliers usually need a new or updated PPAP when:
- A new part or a new part number is introduced
- An engineering change affects the design, specification, or material
- Tooling is new, replaced, refurbished, or moved to another location
- The production process or method changes
- A sub-supplier or material source changes
- Tooling has been inactive for an extended period, often twelve months or more
- A previous submission was rejected and the issue has been corrected
When in doubt, the supplier notifies the customer before making the change and agrees on whether a new submission is needed.
PPAP outside the automotive industry
Companies in other sectors use PPAP because it answers a universal question: can this supplier build this part correctly, every time? It is common when launching wire harness programs or new electronics manufacturing services projects, where many components and process steps must be controlled. Some customers ask for a reduced set of elements, while others use the full Level 3 package for every new part. Agreeing on the level early avoids surprises at launch.
Frequently asked questions
What does PPAP stand for?
PPAP stands for Production Part Approval Process. It is the method suppliers use to show a customer that their process can consistently produce parts that meet every requirement.
What is the difference between PPAP and a first article inspection?
A first article inspection checks that the first part from a new setup matches the drawing. PPAP goes further: it also covers the process documentation, risk analysis, measurement system, and capability studies that show the process will keep producing good parts.
How long does a PPAP take?
It depends on the part, the submission level, and how much of the documentation already exists. A simple Level 1 submission can be quick, while a full Level 3 package for a new part requires the complete production run, measurements, and studies before it can be sent.